INTEL SUPER LOAD VIOLET TOWNSHIP RESIDENTS AND SURROUNDING COMMUNITY
The super load is passing through our area. The schedule below are the expected dates that the Intel Super load will move through our area: Sunday, March 10, day 5 and Monday, March 11 day 6. Please note these are projected dates from ODOT and travel may need to be adjusted.
03/10/24 - Day 5
6:00 a.m. Tailgate Talk
7:00 a.m. Departure (approximate)
Travel East on Bixby Road to US Route 33
Travel East in the Westbound lanes of US Route 33 to the Gender Road Southbound to US Route 33 Westbound ramp in Canal Winchester
Travel the wrong way on the Gender Road Southbound to US Route 33 Westbound ramp
Take State Route 674/Gender Road North to Brice Road
Take Brice Road North to the intersection with Tussing Road/State Route 204 in Columbus
Travel East on Tussing Road/State Route 204 East toward State Route 310
03/11/24 - Day 6
8:00 a.m. Tailgate Talk
9:00 a.m. Departure (approximate)
Continue East on Tussing Road/State Route 204 to State Route 310
Travel North on State Route 310 to US Route 40 in Etna
Travel East on US Route 40 to State Route 79 in Hebron
Travel the wrong way on the State Route 79 Southbound off ramp to US Route 40
Travel North in the Southbound lanes on State Route 79 to local roads
Loads delivered to final destination
Matt Bruning
ODOT Press Secretary
614-512-5121